Coordination strategy
One schedule, shared

When a date moves, everyone moves with it.

A renovation is a relay. Each trade hands off to the next, so a single slip early in the job pushes everything behind it. Here's how we keep the whole supplier group on one timeline — automatically — when a project moves forward or falls back.

The problem

One phone call short of chaos.

Today, when a job slips, the update travels by phone tag. The coordinator calls the cabinet installer, forgets the countertop shop, texts the electrician, and the appliance delivery shows up on the original date to a kitchen that isn't ready. Someone always misses the memo — and a missed memo means a wasted truck roll, an idle crew, or a install done out of order.

The schedule lives in a dozen places at once: our project plan, the GC's notebook, each supplier's own calendar. The moment one of them changes, the others are wrong.

The idea

Everyone reads from the same living schedule.

The project timeline already lives in one place — the client's Project Plan. It's the single source of truth, and it already knows how to cascade: move one phase and every phase after it slides by the same amount, each keeping its own length.

The shift

Instead of every supplier keeping their own copy of the dates, every supplier subscribes to the one schedule. When the coordinator moves a date, the change ripples down the trades and lands in each supplier's own calendar — without a single phone call.

Rough-in
Flooring
Cabinets
Countertops
Fixtures & light
Appliances

Every supplier reads from the one schedule at the centre — so when it moves, they all move.

Why one change moves everyone

The trades are a chain.

Each trade depends on the one before it being finished. That dependency is exactly why a single delay ripples forward — and exactly what lets us shift everyone correctly with one move.

Rough-inPlumb & wire
›
FlooringSubfloor & tile
›
CabinetsInstall
›
CountertopsTemplate & set
›
Fixtures & lightingHook-up
›
AppliancesDeliver & fit
A worked example

The flooring runs a week late.

Say the flooring crew hits a supply delay and finishes one week later than planned. The cabinet installers can't start on bare subfloor, so their week moves too — and countertops (templated off the cabinets), then fixtures, lighting and appliances, all shift by the same week. One move, applied once, updates the whole back half of the job.

Before — the planned schedule
Flooring
Cabinets
Countertops
Fixtures / light
Appliances
After — flooring +1 week, everything downstream follows
Flooring
Cabinets
Countertops
Fixtures / light
Appliances

Flooring stretches by a week — and cabinets, countertops, fixtures, lighting and appliances each slide a week to the right, keeping their own length and the gaps between them. The coordinator makes one change; every supplier sees their new date.

The delay Build trades Finish trades
How every supplier stays in sync

Subscribe once. Get told. Confirm.

The magic isn't a new date — it's that the new date reaches everyone the same minute it changes. Three simple pieces make that happen:

01 · Subscribe

A live calendar link

Each supplier subscribes to the project once — a single calendar link in their phone or Outlook. Unlike a one-time "add to calendar," a subscription refreshes on its own, so their dates are always the current dates.

02 · Get told

An automatic heads-up

The instant a date they're on moves, they get a note: "Your cabinet install moved from Mar 10 to Mar 17." No chasing, no group texts — only the suppliers actually affected are told, and only about their part.

03 · Confirm

One-tap acknowledgement

The supplier taps Confirm to lock the new date — or flags a conflict. The coordinator sees at a glance who's locked in, so the new plan is real, not assumed.

Who moves the dates

One hand on the master schedule.

Only one person moves a date — the project coordinator — so the schedule never forks. Suppliers don't edit the timeline; they flag and confirm. That keeps a single, trustworthy version for the whole group.

Supplier flags"We're running a week behind on flooring."
Coordinator movesShifts flooring; the cascade updates everyone downstream.
Everyone's toldOnly affected suppliers get their new dates.
All confirmOne tap each — the new plan is locked.
Why it's worth it

Fewer wasted trips. Fewer idle days.

No wasted truck rolls.

Appliances don't arrive to an unfinished kitchen; crews don't show up to a job that isn't ready for them.

No idle crews.

When a date opens up because the job moved forward, the next trade can pull in early instead of waiting.

Trust across the group.

Every supplier knows the dates they're looking at are the real, current dates — not last week's.

A faster finish.

Slack gets squeezed out of the schedule because changes propagate in minutes, not days of phone calls.

What it takes to build

We're most of the way there.

The hard part — the cascade math — already lives in the plan's adjustable timeline: move one phase and the rest follow. To turn that into a shared feed, we add three things: a live per-project calendar link each supplier can subscribe to, a small notification step when dates change, and a confirm tap. That live feed needs a lightweight hosted service behind it — the one piece a static page can't do on its own.

The natural next step: today the plan lets a homeowner add the schedule to their own calendar as a one-time export. The supplier version makes that link live and shared — so the same cascade that already keeps the homeowner current keeps every trade current too.
The whole idea, in one line

Change the schedule once — and the whole crew is already looking at the new plan.

One living timeline, one hand moving it, and every supplier reading from the same page.